Solar Pass Project

0
0

We were approached by the client with a difficult but very interesting project build. The Client was after an extension to his existing factory in Bibra Lake. The build requires us to form, pour and erect an extension to a existing 14m high factory. Issues where to have this build take place while the original building is still in use. We have had to create a plan that takes into consideration the removal of 6, 12 m high structural panels while maintaining its physical and operational integrity. Then preform an erection of 30 new panels connecting to the original building, of course, all within a suitable cost.